Rajasthan has auctioned more mineral blocks than any other Indian state, 140 by July 2026, of which 8 are operational. The Ministry of Mines gave both figures to the Rajya Sabha on 27 July 2026.

Sol Gravitas traced, stage by stage through government records, where each mining lease block stood on 1 and 2 November 2026. The main count covers the 75 blocks that state records show as auctioned from December 2020 to December 2025. Nearly all are limestone blocks, most of them won by cement companies. Blocks offered from December 2025 onward are reported separately, because most have had less than a year to move.

57 of 58live blocks have an approved mining plan
20 of 58live blocks have environmental clearance
759 daysmedian from auction to clearance, blocks cleared by the state authority
  • Most live blocks have a mining plan. Of 58 blocks whose auction result stands, 57 have an approved mining plan.
  • Fewer have environmental clearance. 20 of the 58 have clearance. Only 5 appear in the state's lease register.
  • After clearance, the record thins out. Only Parewar-B has every later step on public record, from lease to output. Output is also on record for three Nagaur blocks auctioned in 2016 to 2018. For one block cleared in January 2025, the company reported in October 2025 that the lease deed had not been executed.
  • Blocks cleared by the state authority took a median of 759 days from auction to clearance. Measured from the application date the portal shows, the median was 59 days; that date can be later than the first filing.
  • Larger blocks needing central clearance have moved fewer stages. Of 25 live blocks that need it, 3 have it. For seven, the latest clearance application shows on the portal as "Delisted by system". The oldest of these blocks was auctioned in December 2021.
  • The state has started clearing blocks before auction. Eight small blocks were auctioned with clearance already in place, and the clearances moved to the winner 86 days after the auction.
  • The state rejected 15 winning bids: 13 in 2024, for which its published list gives no reason, and 2 in December 2025, for a reason the bidders' filings quote.

For suppliers to mines, the 20 cleared blocks and the eight blocks cleared before auction are the furthest along in the records. What this means for suppliers to mines lists them by name.

The study uses only government records, company stock exchange filings and companies' own compliance reports, read on 1 and 2 November 2026.

How this was checked
Auction result
The state Directorate of Mines and Geology's list of auctioned blocks dated 13 December 2024, plus its 59 notices from 2024 to 2026: preferred bidders, qualified bidders, annulments, holds and the 2026-27 auction calendar.
Mining plan
The Indian Bureau of Mines national list of mining plans (3,489 entries, 3 August 2022 to 30 October 2026) and its Ajmer region reports.
Environmental clearance
PARIVESH, the Ministry of Environment's clearance portal: full exports for Rajasthan mining, central and state, plus each proposal's history. Clearances before 2022 come from the older portal.
Lease
The state's public register of lease holders, all 3,449 major mineral leases, queried division by division.
After clearance
Documents companies filed on PARIVESH with later applications (lease orders, pollution board consents, mining office output certificates and the Ministry of Environment regional office's compliance report), companies' own six-monthly compliance reports, and Indian Bureau of Mines inspection reports.
Totals and operation
Rajya Sabha and Lok Sabha replies by the Ministry of Mines, and the Ministry's year-by-state auction table.
Company filings
Where a winner or a rejection is not published by the state, the company's stock exchange filing is used and named as such.
Retrieved
1 and 2 November 2026.
Cross-checked
Where a second record exists, figures were checked against it: winners against the Indian Bureau of Mines list and company filings, totals against two separate Parliament replies, and Parewar-B's dates across several documents. Where no second record exists, the gap is stated in Limits. Counts were also rebuilt by a second, independent pass from the source files, which found two errors, both corrected: one clearance filed under another name, and one correction notice mistaken for a clearance.
Checked by hand
Ashoksingh Chauhan checked 15 key figures against the live records and the original documents. One date was off by a day because of a time-zone setting; all such dates were corrected.
Named source
Every figure in this study names the record it comes from (see Sources).

Rajasthan has auctioned more blocks than any other state. About 6% of its auctioned blocks are operational (8 of 140), against about 15% for India as a whole (105 of 720). Both counts include composite licence blocks, which must be explored before they can be mined.

Rajasthan auctioned the most blocks in India, and 8 of 140 are operationalMineral blocks auctioned since 2015 and operational, states with 14 or more auctionedAuctionedOperationalRajasthan, operationalAll India: 105 of 720 operational (15%)RajasthanRajasthan: 140 auctionedRajasthan: 8 operational8 of 140 (6%)Madhya PradeshMadhya Pradesh: 127 auctionedMadhya Pradesh: 10 operational10 of 127 (8%)OdishaOdisha: 74 auctionedOdisha: 35 operational35 of 74 (47%)KarnatakaKarnataka: 65 auctionedKarnataka: 18 operational18 of 65 (28%)ChhattisgarhChhattisgarh: 64 auctionedChhattisgarh: 5 operational5 of 64 (8%)GujaratGujarat: 58 auctionedGujarat: 14 operational14 of 58 (24%)Andhra PradeshAndhra Pradesh: 47 auctionedAndhra Pradesh: 5 operational5 of 47 (11%)MaharashtraMaharashtra: 45 auctionedMaharashtra: 3 operational3 of 45 (7%)Tamil NaduTamil Nadu: 24 auctioned0 of 24 (0%)GoaGoa: 18 auctionedGoa: 6 operational6 of 18 (33%)AssamAssam: 14 auctionedAssam: 1 operational1 of 14 (7%)
Source
Rajya Sabha Unstarred Question 908, Annexure I, answered 27 July 2026. All India covers every state in the annexure.

A Lok Sabha reply of 12 August 2026 gives the same 8 for Rajasthan. Counting mining lease blocks only, it says lease deeds had been executed for 117 of 459 auctioned nationally, and 105 of these had commenced mineral production, about 23%. Rajasthan's 140 include 30 composite licence blocks, so its share on the same basis is about 7%.

The pace of auctions is rising. The Ministry's year-by-state table shows Rajasthan auctioned 7 blocks in 2021-22 and 38 in 2025-26. Most of the 140 were auctioned in the last three years, and a recently auctioned block has had less time to move through the stages that follow.

Of the 75 blocks auctioned, 58 are live. The state rejected 15 winning bids, one auction was cancelled (Bhukia-Jagpura) and one block was auctioned again (Bagawas). Of the 58, 57 are limestone and one is iron ore. Twenty-five need clearance from the Ministry of Environment and 30 from the state authority; for the other three, no clearance filing was found or the block was not checked. In this study the larger blocks, about 290 ha and up, go to the Ministry, and the smaller ones, about 200 ha and below, to the state authority.

Almost every live block reaches an approved mining plan: 57 of the 58 have one. After that the count falls at each step. A third of the live blocks have not yet applied for environmental clearance, and nearly half of those that applied are still in process or delisted.

Of 75 blocks auctioned, 20 have clearance and 5 are in the lease registerState-auctioned mining lease blocks, Rajasthan, December 2020 to December 2025, status on 1 November 2026AuctionedAuctioned: 75 blocks75 (100%)Mining lease results, December 2020 to December 2025Result still standsResult still stands: 58 blocks58 (77%)15 bids rejected by the state, 1 auction cancelled, 1 block re-auctionedMining plan approvedMining plan approved: 57 blocks57 (76%)1 not yet filed: Kishanpura, auctioned December 2025Clearance applied forClearance applied for: 38 blocks38 (51%)20 not yet applied: 17 at terms-of-reference stage, 2 nothing filed, 1 not checkedClearance grantedClearance granted: 20 blocks20 (27%)10 applications delisted by the portal, 8 still in processIn state lease registerIn state lease register: 5 blocks5 (7%)Parewar-B, Khinya-II A, Sindwari, TKSB 18, TKSB 24
Source
Sol Gravitas block register built from state auction lists and notices, the Indian Bureau of Mines mining-plan list, PARIVESH and the state lease register, read 1 and 2 November 2026.

Across the 57 blocks with a plan, the median time from auction to an approved plan was 326 days, and no block took more than 631.

Blocks offered later. Besides the 75, the state offered 24 more mining lease blocks between December 2025 and June 2026. Twenty are confirmed auctioned. Most are at the mining plan stage or earlier.

How the 140 adds up

State records confirm 130 state auctions to June 2026. The central government ran five more in Rajasthan:

  • two potash blocks in Hanumangarh
  • two rare earth blocks in Balotra
  • the Karna rare earth block

That makes 135, and up to 139 if four auctions with no published result went through.

For the 20 blocks that have clearance, the stage from application to clearance was the shortest. Most of the time passed before the application.

Smaller blocks took a median of 759 days to clearance, 59 of them after applyingDays from auction to environmental clearance, by stage, for the 20 auctioned mining lease blocks that have itAuction to mining planMining plan to applicationApplication to clearanceEight blocks cleared before auction: clearance moved to the winner 86 days after auctionCleared by the state authority (17 blocks, median 759 days)TKSB 37TKSB 37: auction 2024-07-05 to mining plan approved 2025-02-27, 237 daysTKSB 37: mining plan to clearance application 2025-07-04, 127 daysTKSB 37: application to clearance granted 2025-11-13, 132 days496 daysTKSB 24TKSB 24: auction 2024-06-18 to mining plan approved 2025-06-18, 365 daysTKSB 24: mining plan to clearance application 2026-01-12, 208 daysTKSB 24: application to clearance granted 2026-02-11, 30 days603 daysTKSB 18TKSB 18: auction 2024-06-07 to mining plan approved 2025-06-16, 374 daysTKSB 18: mining plan to clearance application 2026-01-12, 210 daysTKSB 18: application to clearance granted 2026-02-11, 30 days614 daysFalwaFalwa: auction 2024-12-02 to mining plan approved 2025-07-14, 224 daysFalwa: mining plan to clearance application 2026-08-07, 389 daysFalwa: application to clearance granted 2026-10-10, 64 days677 daysNB 11NB 11: auction 2024-09-23 to mining plan approved 2025-08-16, 327 daysNB 11: mining plan to clearance application 2026-08-22, 371 daysNB 11: application to clearance granted 2026-10-10, 49 days747 daysNB 08NB 08: auction 2024-09-18 to mining plan approved 2025-07-22, 307 daysNB 08: mining plan to clearance application 2026-08-22, 396 daysNB 08: application to clearance granted 2026-10-10, 49 days752 daysNB 07NB 07: auction 2024-09-17 to mining plan approved 2025-08-09, 326 daysNB 07: mining plan to clearance application 2026-08-22, 378 daysNB 07: application to clearance granted 2026-10-10, 49 days753 daysNB 06NB 06: auction 2024-09-12 to mining plan approved 2025-07-24, 315 daysNB 06: mining plan to clearance application 2026-08-22, 394 daysNB 06: application to clearance granted 2026-10-10, 49 days758 daysNB 05NB 05: auction 2024-09-11 to mining plan approved 2025-08-21, 344 daysNB 05: mining plan to clearance application 2026-08-22, 366 daysNB 05: application to clearance granted 2026-10-10, 49 days759 daysNB 04NB 04: auction 2024-09-10 to mining plan approved 2025-08-22, 346 daysNB 04: mining plan to clearance application 2026-08-22, 365 daysNB 04: application to clearance granted 2026-10-10, 49 days760 daysPSB12PSB12: auction 2024-03-01 to mining plan approved 2025-02-08, 344 daysPSB12: mining plan to clearance application 2026-05-23, 469 daysPSB12: application to clearance granted 2026-07-21, 59 days872 daysPSB11PSB11: auction 2024-02-29 to mining plan approved 2025-02-08, 345 daysPSB11: mining plan to clearance application 2026-05-23, 469 daysPSB11: application to clearance granted 2026-07-21, 59 days873 daysPSB07PSB07: auction 2023-09-19 to mining plan approved 2024-11-12, 420 daysPSB07: mining plan to clearance application 2026-05-06, 540 daysPSB07: application to clearance granted 2026-07-18, 73 days1,033 daysPSB06PSB06: auction 2023-09-18 to mining plan approved 2024-11-07, 416 daysPSB06: mining plan to clearance application 2026-05-06, 545 daysPSB06: application to clearance granted 2026-07-18, 73 days1,034 daysPSB02PSB02: auction 2023-09-12 to mining plan approved 2024-11-08, 423 daysPSB02: mining plan to clearance application 2026-05-06, 544 daysPSB02: application to clearance granted 2026-07-18, 73 days1,040 daysPSB01PSB01: auction 2023-09-11 to mining plan approved 2024-11-06, 422 daysPSB01: mining plan to clearance application 2026-05-06, 546 daysPSB01: application to clearance granted 2026-07-18, 73 days1,041 daysSindwari Charliya ASindwari Charliya A: auction 2022-02-15 to mining plan approved 2023-08-28, 559 daysSindwari Charliya A: mining plan to clearance application 2025-09-02, 736 daysSindwari Charliya A: application to clearance granted 2026-03-14, 193 days1,488 daysCleared by the Ministry of Environment (3 blocks, median 511 days)Parewar-BParewar-B: auction 2020-12-10 to mining plan approved 2021-05-27, 168 daysParewar-B: mining plan to clearance application 2021-10-23, 149 daysParewar-B: application to clearance granted 2022-03-17, 145 days462 daysKhinya-II AKhinya-II A: auction 2021-02-15 to mining plan approved 2021-08-09, 175 daysKhinya-II A: mining plan to clearance application 2022-05-27, 291 daysKhinya-II A: application to clearance granted 2022-07-11, 45 days511 days4G-IIa4G-IIa: auction 2021-02-16 to mining plan approved 2022-02-08, 357 days4G-IIa: mining plan to clearance application 2023-09-22, 591 days4G-IIa: application to clearance granted 2025-01-02, 468 days1,416 days
Source
Sol Gravitas block register from state auction lists, the Indian Bureau of Mines mining-plan list, PARIVESH and the older clearance portal. Application date is the submission date the portal shows. Read 1 and 2 November 2026.

For the 17 blocks cleared by the state authority, the median from auction to clearance was 759 days. By stage, the median was 345 days from auction to an approved mining plan, then 394 days from the plan to the clearance application, then 59 days from the application to clearance. Stage medians do not add up to the overall median, because each is the middle value of its own stage. In between plan and application, a company needs terms of reference for an environmental study, then the study itself, which usually includes a public hearing held by the state pollution control board. The records do not show how that time divides between the companies, their consultants and the authorities.

A note on application dates

The application date used here is the submission date the portal shows, and it can be later than the first filing. For Sindwari the portal shows 2 September 2025, while the proposal's history shows it first submitted on 7 August 2025.

The longest stage from application to clearance was for 4G-IIa: 468 days, with four rounds of requests for more information. The eight blocks the state cleared before auction skipped the early steps. Their clearances moved to the winner 86 days after the auction (see What has changed since 2024).

Larger blocks without central clearance. Twenty-two live blocks need clearance from the Ministry of Environment and do not yet have it. Fourteen were auctioned from 2021 to 2024. For seven of these, PARIVESH showed the latest clearance application as "Delisted by system" on 1 November 2026.

See the seven blocks and dates
Block Winner in the records Auctioned Terms of reference granted Delisted by system on
Rata-Mandha-1A Deccan Cements Dec 2021 Jan 2024 11 Sep 2026
3D2 Ambuja Cements Dec 2021 Jan 2024 3 Sep 2026
3C1 JSW Cement Jan 2022 Jan 2024 1 Apr 2026
3C2 JSW Cement Jan 2022 Jan 2024 1 Apr 2026
4G-I-a JK Lakshmi Cement Apr 2022 Feb 2024 21 Feb 2026
HPB 20 Ambuja Cements Oct 2023 Nov 2024 3 Sep 2026
Chandakheri-Shadi-Palka JK Cement May 2024 Nov 2025 20 Sep 2026

A delisting means the portal's time limit for a reply passed. The record does not show why, and an applicant may let an application lapse for its own reasons, for example to revise it. Sol Gravitas did not ask the companies. Delisting is not final: the portal allows an application to be revived. Each of the ten clearance applications filed for these fourteen blocks has been delisted at least once. Three were revived and are in process (Ramgarh, Nimana-Duniya and HPB 19). The other four blocks have not yet applied for clearance: Gothra Parasrampura West and East, which have held terms of reference since January 2024, Joga-II and Khuiala South. Of the eight central-clearance blocks auctioned in 2025, only Parewar (SN-I) has applied, in September 2026.

Smaller blocks without clearance. Thirteen live blocks that go to the state authority do not yet have clearance. Three applications show as delisted (Hariyav Jaspura, TKSB 38 and NB 10), four are in process (TKB 11 and NB 01 to NB 03) and six blocks have not yet applied (TKSB 17, 23, 30 and 31, Tadas-I and Tadas-II).

After environmental clearance, a block still needs a registered lease and the state pollution board's consent to establish and then to operate. Some blocks also need forest clearance or permission to mine pasture land. Sol Gravitas looked for each of these steps for the 20 cleared blocks, the eight blocks cleared before auction, and three Nagaur blocks auctioned in 2016 to 2018. The records searched were documents filed on PARIVESH, company compliance reports, Indian Bureau of Mines inspection reports and the state lease register.

One block has every step on record. Parewar-B in Jaisalmer, won by Wonder Cement, is the only block in the study whose full path from auction to output is on public record. The documents are filed with the company's 2026 application to expand the mine.

Step Date Record
Auction 10 Dec 2020 State list of auctioned blocks
Letter of intent 25 Jan 2021 State lease grant order
Forest department no-objection, for non-forest land 22 Apr 2021 Deputy Conservator of Forests, Jaisalmer
Mining plan approved 27 May 2021 Indian Bureau of Mines
Environmental clearance 17 Mar 2022 Ministry of Environment
Lease granted 10 Aug 2022 State Mines and Petroleum Department
Lease registered 10 Oct 2022 Mining Engineer, Jaisalmer
Consent to establish 11 Nov 2022 State pollution board
Consent to operate, 1.4 million tonnes a year, valid to 30 Nov 2027 13 Dec 2022 State pollution board
First year with recorded output 2023-24 Mining Engineer, Jaisalmer

From auction to consent to operate took 733 days, and from clearance to consent to operate, 271. The Mining Engineer, Jaisalmer, certifies run-of-mine output of 0 tonnes in 2022-23, 751,210 tonnes in 2023-24, 205,103 tonnes in 2024-25 and 179,461 tonnes in 2025-26. In a certified compliance report dated 25 June 2026, the Ministry of Environment's regional office records the project as "in operational phase". Wonder Cement has applied to raise capacity from 1.4 to 7.84 million tonnes a year. Since 21 October 2026 the application has shown "ADS raised", meaning additional details were sought.

The other blocks. For the rest, the record is partial. The table shows what each record says, oldest clearance first.

See the record for each cleared block
Block Clearance Lease Consent to operate Output on record
3B1A, Nagaur (Nu Vista) Before 2022 In state register Not found Mine opened 13 Dec 2021; 21,071 tonnes in 2022-23
3B1B, Nagaur (Nu Vista) Before 2022 Executed 28 Dec 2018 Not found Mine opened 13 Dec 2021; output reported for 2023-24
3B2, Nagaur (JSW Cement) Before 2022 Executed April 2023 (company report) Held (company report) Mining commenced March 2025 (company report)
Parewar-B, Jaisalmer (Wonder Cement) 17 Mar 2022 Registered 10 Oct 2022 13 Dec 2022 From 2023-24
Khinya-II A, Jaisalmer (JK Cement) 11 Jul 2022 In state register 31 Aug 2023, 5.5 million tonnes a year, valid to 31 Jul 2028 Nil to September 2025 (company reports)
4G-IIa, Nagaur (Hansdeep, merged into JK Lakshmi Cement in 2025) 2 Jan 2025 "Till date Lease Deed is not executed" (company report, 1 Oct 2025) Not found "No activities started yet" (same report)
TKSB 37, Nagaur (Sigma Minerals) 13 Nov 2025 Not in state register Not found None found
TKSB 18, TKSB 24, Nagaur (Suncity Chemical and Minerals) 11 Feb 2026 In state register Not found None found
Sindwari Charliya Block-A, Chittorgarh (JK Cement) 14 Mar 2026 In state register Not found None found
JMK-01 to JMK-08, Jodhpur (BLA Projects) Transferred 19 Jun 2026 Not in state register Not found None found
PSB01, PSB02, PSB06, PSB07, PSB11, PSB12, Nagaur (Ambuja Cements) 18 and 21 Jul 2026 Not in state register Not found None found
NB 04 to NB 08 and NB 11, Beawar (Star Cement North East) 10 Oct 2026 Not in state register Not found None found
Falwa, Chittorgarh (Wonder Cement) 10 Oct 2026 Not in state register Not found None found

"Not found" means not found in the records searched on 1 and 2 November 2026. The state pollution board's consent search could not be reached on those days.

Forest and pasture land. Of 80 forest clearance proposals for mining in Rajasthan on PARIVESH, one is for a block in this study: 105.149 ha of forest land for Block 4G-I-a (JK Lakshmi Cement, a different block from 4G-IIa), submitted 23 September 2025. It shows as "Pending at PP due to EDS by DFO", meaning it is with the applicant after the divisional forest officer sought essential details. That block does not yet have environmental clearance. The forest no-objections on record for Parewar-B and Khinya-II A are for non-forest land. For pasture (charagah) land, the state's post-auction guidance lists a Revenue Department no-objection. Khinya-II A's compliance reports state that 43.03 ha of its lease area is grazing land and that it will not be diverted at any stage of mining. No other block's pasture-land position was found on public record.

The records answer where each block stands. They rarely say why.

The records show four developments since 2024: clearance obtained before auction, rejection of winning bids, new deadlines in the auction rules, and an auction calendar that marks the Great Indian Bustard boundary.

Clearance before auction. The Rajasthan State Mineral Exploration Trust applied for environmental clearance on eight small limestone blocks near Jhak and Murkasani, Jodhpur (JMK-01 to JMK-08, 4 to 6 ha each). The state authority granted it on 4 November 2025.

The state's 2026-27 auction calendar plans seven more blocks with clearances built in, at Khuiala, Jaisalmer. Clearance applications for several Khuiala blocks were filed by the same trust in July to October 2026.

Rejection of winning bids. The state can reject a winning bid under Clause 14.11 of its tender document.

This study counts all 15 as not live. The state's list of 13 December 2024 still includes the 13 rejected that year, each marked as rejected.

New deadlines in the auction rules. The Ministry of Mines notified intermediate timelines on 17 October 2025. The rules provide for appropriating 1% of a bidder's performance security for each month of delay attributable to the bidder; the amount can be adjusted against the auction premium if the final milestone is met on time. A state that is late issuing the letter of intent gets 5% less of the second upfront instalment for each month. A lessee pays only half the auction premium on minerals produced within five years of the letter of intent.

Source
Rajya Sabha reply, 2 February 2026.

The Great Indian Bustard boundary. The 2026-27 calendar marks 14 of its named future blocks as inside the Great Indian Bustard boundary, all in Jaisalmer. Nine fall outside it. The calendar records this as a status note and gives no further detail.

A block's need for equipment, explosives, transport and services generally grows as it moves toward production. In the records, the step before that is environmental clearance, and 28 blocks have it. The table lists them, newest clearance first.

This is not a forecast. After clearance a block still needs a registered lease and the state pollution board's consents, and some need forest or pasture-land permission. For most of the blocks below, those steps are not yet on public record. The section After clearance sets out what the records show for each block.

Block District Winner in the records Area (ha) Clearance granted In state lease register, 1 Nov 2026
NB 04, NB 05, NB 06, NB 07, NB 08, NB 11 (6 blocks) Beawar Star Cement North East 8.4 to 33.9 each 10 Oct 2026 No
Falwa Chittorgarh Wonder Cement 12.0 10 Oct 2026 No
PSB11, PSB12 (2 blocks) Nagaur Ambuja Cements 4.8 each 21 Jul 2026 No
PSB01, PSB02, PSB06, PSB07 (4 blocks) Nagaur Ambuja Cements 4.8 each 18 Jul 2026 No
JMK-01 to JMK-08 (8 blocks, cleared before auction) Jodhpur BLA Projects 4.1 to 6.2 each Transferred 19 Jun 2026 No
Sindwari Charliya Block-A Chittorgarh JK Cement 203.6 14 Mar 2026 Yes
TKSB 18, TKSB 24 (2 blocks) Nagaur Suncity Chemical and Minerals 4.8 each 11 Feb 2026 Yes
TKSB 37 Nagaur Sigma Minerals 4.8 13 Nov 2025 No
4G-IIa (cleared as "Tadawas") Nagaur Hansdeep Industries and Trading 424.0 2 Jan 2025 No
Khinya-II A Jaisalmer JK Cement 304.0 11 Jul 2022 Yes
Parewar-B Jaisalmer Wonder Cement 515.2 17 Mar 2022 Yes

Three things stand out for a supplier.

The Ministry's replies to Parliament count 8 operational blocks in Rajasthan but do not name them. The state register shows exactly 8 leases from the auction era: these 5, plus three Nagaur blocks auctioned in 2016 to 2018. This study could not confirm from public records whether these are the 8 the Ministry counts.

Output is on public record for four of these eight: 3B1A, 3B1B, 3B2 and Parewar-B. Khinya-II A holds consent to operate, and its company reports show nil output to September 2025. No output record was found for Sindwari, TKSB 18 or TKSB 24.

Blocks offered from December 2025 onward are earlier in the process; see Where the auctioned blocks stand.

Block register. All 99 blocks in one spreadsheet: auction date, winner as recorded, mining plan, clearance proposals and portal dates, lease status, and the records used for each entry.

Download the block register (CSV)

Data report. The same figures as tables: every block and every number with its source and status date, the method and the limits, in one PDF. What a commissioned brief looks like.

Download the data report (PDF)
Limits and definitions

The records answer where each block stands. They rarely say why. Where this study reports the time a block has taken or a delisted application, it does not say who or what caused it.

Steps after clearance are partly on record. Lease dates, consents and output in this study come from documents companies filed on PARIVESH or published themselves, and from Indian Bureau of Mines inspection reports. The state pollution board's consent search could not be reached on 1 and 2 November 2026. "Not found" in the After clearance table means not found in these records on those dates.

Lease register is not production. A lease in the state register is not proof of mining. Sindwari's clearance letter of March 2026 calls it "a proposed limestone mine" while the register lists its lease from 2022. So a lease in the register may not mean mining has started.

Output figures differ by record. For Parewar-B in 2023-24, an Indian Bureau of Mines letter gives 505,007 tonnes and the state mining office certifies 751,210 tonnes run-of-mine. This study quotes the state certificate as labelled and does not reconcile the two.

The 8 operational blocks are not named. Parliament gives only the count.

Composite licence blocks not tracked. The 30 composite licence blocks (explore first, then mine) were counted but not followed stage by stage.

2026 winners partly unknown. Of 24 mining lease blocks offered from December 2025 to June 2026, 20 are confirmed auctioned and winners are on record for 14. For the other four, no result has been published.

Some results come from company filings. Four 2026 winners and the two December 2025 rejections rest on the companies' own stock exchange filings, not state notices.

Year counts differ slightly. The Ministry's year-by-state table shows 0 Rajasthan auctions in 2020-21, while state records show 3 that year. The total to 2020-21 is 8 either way. This study uses the auction dates in state records.

Totals reconcile, not exactly. State records and Parliament replies account for 135 of the 140 auctioned blocks with confirmed results, and up to 139. The rest could not be matched to a published result.

One iron ore block not checked. Bagawas, re-auctioned in 2025, was not searched in the clearance records.

Definitions

Live block. a mining lease block whose auction result stands. Blocks whose bid was rejected, whose auction was cancelled, or which were re-auctioned are not live.

Delisted application. an application PARIVESH shows as "Delisted by system". The portal removes an application automatically when a request for information is not answered in time. Under a Ministry of Environment order of 25 October 2024, the limits are 30 days for essential details and 90 days for additional details. A delisted application can be revived.

Days to clearance. calendar days from the auction date to the date the environmental clearance was granted.

Status date and corrections. Statuses are as shown on official portals on 1 and 2 November 2026 and may have changed since. This study is not investment or legal advice. Corrections: info@solgravitas.com

Sources

Parliament and the Ministry of Mines

Government of Rajasthan

Mining plans and environmental clearance

After clearance

  • PARIVESH, documents filed with Wonder Cement's Parewar-B expansion application IA/RJ/MIN/589385/2026: lease grant order, lease deed, pollution board consents, forest no-objection, mining office output certificate and the regional office's certified compliance report RO/RJ/CCR/653237/2026, read 2 November 2026
  • PARIVESH, documents filed with the 4G-IIa (Tadawas) clearance IA/RJ/MIN/445238/2023: six-monthly compliance report dated 1 October 2025, read 2 November 2026
  • PARIVESH forest clearance search, Rajasthan, mining and quarrying, all years, 2 November 2026
  • JK Cement, Khinya-II A environmental compliance report, April to September 2025, company website, and its earlier reports from April 2022
  • JSW Cement, 3B2 environmental compliance report, October 2024 to March 2025, company website
  • Indian Bureau of Mines inspection reports: Nagaur (03/2016) Block-3, that is 3B1A, inspected 5 February 2024; Nagaur 3B1B, virtual inspection 13 February 2025
  • Directorate of Mines and Geology, Post Auction Facilitation page: steps after auction, including the Revenue Department no-objection for charagah land

Company stock exchange filings

The full block register (75 mining lease blocks from December 2020 to December 2025, and 24 offered from December 2025 to June 2026) is free to download as a CSV file, with the records used for every entry, together with a data report (PDF) that sets out every figure as tables.